A proposal for
5712 W Vineyard Rd · Laveen, Arizona 85339
Complete price · labor and materials
$8,560
Base scope as drawn. 25% to schedule your pour, the rest when we finish and walk it with you.
Three new slabs, poured over three days on site: a 12-foot driveway extension back to your side gate, a 24 × 16 patio off the back of the house, and a walkway connecting the two. 992 square feet, 4 inches thick, broom finished.
The plan
Drawn to scale from our site visit on September 18. The lettered slabs are new concrete; everything else is what's there today. Tap a slab in the list to find it on the plan.
New concrete, total992 sq ft
The price
Each slab is priced by the square foot, and the rate covers everything it takes to build it. No allowances, no “to be determined.”
| Slab | Area | Rate | Amount |
|---|---|---|---|
| Driveway extension40 × 12 ft, 4 in thick, fiber-reinforced480 sq ft × $8.50 | 480 sq ft | $8.50 | $4,080 |
| Rear patio24 × 16 ft, 4 in thick, fiber-reinforced384 sq ft × $8.50 | 384 sq ft | $8.50 | $3,264 |
| Side walkway32 × 4 ft. Narrow pours take more forming per foot, so the rate is a little higher128 sq ft × $9.50 | 128 sq ft | $9.50 | $1,216 |
| Base scope, complete992 sq ft · labor, materials, equipment, cleanup and haul-off | $8,560 | ||
Arizona transaction privilege tax is already in these numbers. What you see here is what you'd pay, unless you add an option below or we agree on a change together.
Toggle any of these to see them on the plan and in your total. You can change your mind up to the day before we set forms.
Your total
$8,560
Base scope $8,560
How you'd pay
The deposit is part of the total, not on top of it. Check, Zelle, or card; cards carry a 3% processing fee.
Scope
Most surprises on a concrete job come from the second list. We'd rather you read it now than discover it on day one.
How it goes
We're currently booking about two to three weeks out. The exact dates come once the deposit is in.
Text, email, or sign the printed copy. That, plus this proposal, is our agreement. Nothing else to sign.
Once the deposit clears we book your pour and text you the schedule. If the weather shifts, we'll move it and tell you why.
We grade, set the forms, and compact the base. Before we leave, we walk the forms with you: the last easy moment to move a line a foot.
From you: cars out of the driveway, irrigation flagged.The truck arrives early, at first light in warm weather. We place, screed, float, broom, and cut the joints. By afternoon it's done and needs to be left alone.
From you: pets and kids off the new slabs overnight.Forms come off, edges get backfilled, gravel goes back where it was, everything's swept. We walk it together and settle the balance.
Concrete keeps getting stronger for weeks. Rinse off spills when you see them, and hold off on sealer until it's at least 30 days old.
The fine print
Short on purpose. If anything here worries you, ask before you accept; we'd rather answer now.
Questions
If yours isn't here, text Marcus. Photos of your yard are welcome.
Not exactly, and no one's will. New concrete starts light and darkens over its first year, and your old slab has years of sun on it. Where the two meet we set an expansion strip so they can move independently instead of fighting each other.
Not for the work itself. We'd like fifteen minutes with you at the end of day one to walk the forms, and again at the end of day three to walk the finished slabs.
Yes, anything, until the day before we set forms. After that it becomes a change order, and rebar can't be added once the concrete is down.
Every slab does eventually. We cut joints so it cracks in the joints where you can't see it, and we hold the edges thick where the boat will sit. A hairline crack that doesn't move or lift isn't a defect, and isn't something we'd tear out.
Flag anything buried in the three areas before we arrive; a stake and a piece of tape is plenty. We'll cap lines we find, but rerouting them isn't in this price.
Rinse off oil, fertilizer, and pool chemicals when you see them. Keep the boat off for a month. If you want a richer, darker color, we can seal it after 30 days; ask us for a price.
We watch the forecast and won't pour into rain. If it's wet, we slide a day or two and text you the new date. There's no charge for weather.
Next step
Accept as shown and we'll send deposit details and hold your dates. Not sure yet? Call or text Marcus, questions are the point of this page.
This price expired on October 20, 2026. Ready-mix costs move, so we refresh every number before you decide. Ask Marcus for a current version and we'll have it back to you within a day.
Marcus Reyes
Owner, Laveen Flatwork Co. He'll be on site all three days.
Texts answered 6 am to 7 pm, seven days. Site visits and estimates are always free.
Print this page, sign below, and hand it to Marcus or text a photo of it. Either way counts.
HomeownerDaniel Delgado
Date
Laveen Flatwork Co.Marcus Reyes, owner
Date